BULK TRANSFER OF WATER FROM GUNHILL RESERVOIR TO NAGURU RESERVOIR (6,000,000 litres per day)
The bulk transfer is intended to increase water delivered to Naguru reservoir to supply the water stressed, high raised areas of Najjera, Buwatte, Kyanja, Komamboga, Kungu, Kulambilo and parts of Kyebando and Gayaza.
The project includes the following components
• Construction of the booster house at Centenary Park
• Procurement and installations of pumps (three set)
• Laying a pumping main DN250 from Centenary Park to Naguru Reservoir
Progress of the project
• Land to construct booster house at centenary obtained
• Contract for booster house construction awarded
• Contract for supply of pumps awarded
• 3500 meters of pumping main laid
Works have been completed