Objective

The project is aimed at bridging the gap left open by the Uganda Water Management and Development Project (UWMDP);

Description

This phase involves Karuma water treatment plant and bulk water supply to Gulu (including small towns along Gulu highway) and onsite sanitation for private homesteads

Contract Sum

Euros 4.9million (Design & Supervison)

Euros 26million ( Works Budget)

Financiers 

KfW and Government of Uganda

Consultant

Fichtner W & T, GOPA, Infra GmbH

Status of Work 

Preparation of detailed design is in progress

Completion Date

Substantial completion (September 2021)

Final Completion (September 2022)

Objective

The project is aimed at addressing Water Supply and Wastewater Disposal challenges (Industrial Area) in Kapeeka Town

Description

It will follow a phased approach.

Phase 1 entails the following;

  1. Upgrading of the Electromechanical Installations to produce 2,500m3/day
  2. Laying of bulkwater mains from Water Treatment Plant (WTP) to Industrial Park
  3. Commencement of the upgrading of the WTP to produce 7,000m3/day
  4. Ground water investigations and borehole drilling
  5. Design of Wastewater System for the Industrial Park

Phase 2 comprises the following;

  1. Completion of the Water Treatment Plant Upgrade
  2. Development of borehole system
  3. Construction of Sewerage System for the Industrial Park

Budget

UGX 55 Billion.

Financiers

Government of Uganda

Commencement Date

 January 2019

Status of Work

Designing of Water Supply Infrastructure is in Progress.

Objective

The project was developed to replace the old intake for Soroti water supply system that was washed away during the October-November Teso floods of 2010.

Description

The scope of works involves;

Ø  Construction of Intake Structure comprising of inlet sump and pump room

Ø  Supply and installation of 3No. Pumps (including other electro mechanicals) delivering 288m3/h each

Ø  Installation of 125m DN 300mm delivery main

Ø  Supply and installation of standby generator

Ø  Extension of overhead power supply to the new intake plant

Ø  Construction of stabilized murram access road (100m) linking the Intake Works to Soroti Highway

Contract Amount

UGX 5Billion

Financiers

National Water & Sewerage Corporation

Contractor

Ambitious Construction Company Ltd

Supervision Consultant

ILISO Consulting (PTY) LTD

Status of Work

Substantial completion of project works was achieved in July 2016, project under operations during Defects Liability Period.  

System output is currently 5,000m3/day, out of 8,500m3/day (Design Capacity). The output is expected to increase to 7,000m3/day after upstream interventions by the Area at the WTP.

Final Completion Date

July 2017

Objective

The project is aimed at developing new water supply system for Kapeeka town

Description

It involves the following;

Ø  4000m3/d Water intake plant

Ø  4000m3/d Water treatment plant

Ø  600m3 reservoir

Ø  15km Water network (transmission & distribution)

Ø  04No. Staff houses

Contract Amount

Ø  UGX 7.24Billion for Intake & Waterworks

Ø  UGX 790Million for Reservoir

Financiers

National Water & Sewerage Corporation

Contractor

Ø  Vambeco Enterprises Ltd for Intake & Waterworks

Ø  Royal Techno Industries Ltd for Reservoir

Status of Work

Ø  Reservoir works are complete

Ø  11.5km water network are complete

Ø  Staff houses are complete

Ø  Civil works for Water works and Intake plants complete

Ø  Transformer for Water Works was installed

Ø Raw Water Pumps were delivered and installed 

Substantial Completion Date

November 2017

Objective

The project is aimed at addressing wastewater disposal challenges at Kirudu Hospital in Kampala

Description

It involves design, supply, installation and operaion of sewage treatment plant

Budget

UGX 2 Billion.

Financiers

National Water & Sewerage Corporation

Commencement Date

 November 2018

Status of Work

Preparation of Solicitation Documents in Progress.

Objective

The project is aimed at addressing wastewater disposal challenges in towns of Kisoro and Fort[ortal

Description

It Involves design, supply, installation and operation of Sewage treatment plants for both towns.

Contract Amount

UGX 2.3Billion

Contractor

Ecotech Ltd/Enzotech Solutions Private Ltd

Financiers

National Water & Sewerage Corporation

Status of Work

Ø  Kisoro plant is currently under operations, effluent quality meets discharge standards.

Ø Fortportal Plant has been delivered to site. Civil works are in progress. 

Final Completion Date

September 2018 (Substantial Completion)

September 2019 (Final Completion)

Objective

This project aims at increasing capacity of the water treatment plant

Description

It involves construction of additional water treatment units including coagulators and flocculators, clarifiers and filter

Contract Amount

UGX 1.68Billion

Financiers

National Water & Sewerage Corporation

Contractor

Up Deal (U) Ltd

Status of Work

Handling defects and snags is ongoing

System output has increased from 1,700m3/day to 2,300m3/day, this is expected to increase further to 3,700m3/day after replacement of the raw water and treated water pumps in next quarter.

Final Completion Date

August 2017

Objective

Improvement of water supply service in Kapchorwa town

Description

It involves the following;

3,000m3/d Water treatment plant

4km DN 200mm Delivery main

Contract Amount

Ø  UGX 7.3Billion 

Financiers

National Water & Sewerage Corporation

Contractor

Zhonghao Overseas Construction Company Ltd

Status of Work

Ø  Works contract signed, contractor is currently mobilising to commence works

Substantial Completion Date

       

June 2019 (Substantial Completion)

June 2020 (Final Completion)

Objective

The project aims at improvement of water supply and sanitary services in the Mbarara and Masaka service areas and small towns neighbouring Masaka service area including Lukaya, Mpugwe, Kadugala, Butende, Bukulula, Kyamulibwa, Kalungu, Kaliiro, Nabatungwa, Ntale, Kalisizo, Bisanje, Kiziba, Kabuwoko, Nkoni; Kinoni; Kaboyo; Mbirizi.

Description

This project involves the following;

Development of Kagera water treatment plant

Water supply to Isingiro town

Watsan infrastructure improvement in Mbarara, Masaka areas and the neighboring small towns.

Contract Amount

Euros 120 Million.

Financiers

AFD

Consultant

BRL Ingenierie S.A with IGIP and WE consult

Status of Work

Bid evaluation for detailed design and Technical assistance consultants is near completion. 

Objective

The Overall Objective of the project is to improve the quality of life, health and economy of people in the south and west of greater Kampala.

Description

The project involves the development of a new Water intake and treatment plant, primary bulk storage reservoir, associated pumping main, distribution system a Faecal Sludge Treatment Plant and Supply of Water in Informal Settlements in this area.

Budget

Euros 100Million

Financiers

The Royal Danish Embassy in Uganda and National Water & Sewerage Corporation

Status of Work

ØFeasibility study and preparation of conceptual design are in progress

Objective

The project aims at improvement of water supply and sanitary services in Hoima and possible expansion of Watsan services in nearby small towns that are not currently serviced by NWSC.

Description

The project involves the following;

Ø  Rehabilitation of Bigajuka WTP and optimisation of           performance to deliver 8000m3/d

   Ø   Development of Kafu river water supply 

Contract Amount

Euros 34 Million.

Financiers

National Water & Sewerage Corporation

Consultant

Gauff/Gauff Consultants (U) Ltd

Status of Work

Works are expected to be funded by World bank under WMDP Phase 2

Completion Date

Not yet known.

Objective

Improvement of water supply services in the towns of Kyotera, Kalisizo, Mutukula, Rakai & Lyantonde

Description

It involves the following;

Ø  20,000m3/d Water intake plant

Ø  10,000m3/d Water treatment plant

Ø  4000m3 combined storage

Ø  150km Water network (transmission & distribution)

Budget

UGX 40Billion

Financiers

National Water & Sewerage Corporation and Government of Uganda

Status of Work

Ø Evaluation of works tenders for the intake and water treatment component had been completed, Contract signing has since been stayed until further funds are secured.

Objective

The project is aimed at increasing water production from 300m3/day to 3000m3/day and upgrading and extension of the water distribution network.

Description

It involves the following; 

Construction of new intake and water treatment line including; flocculator, coagulator, clarifier, filter and ancillary works. 

Upgrading entire distribution network, and extension to surrounding towns (100km length, 90-200mm)

Contract Amount

UGX 9 Billion.

Financiers

National Water & Sewerage Corporation

Commencement Date

September 2018

Status of Work

Preparation of detail design is in progress

Objective

The project is aimed at improvement in water quality and increase water production by 2500m3/day

Description

It involves construction of flocculator, coagulator, clarifier, filter and ancillary works

Contract Amount

UGX 2.5 Billion.

Financiers

National Water & Sewerage Corporation

Commencement Date

September 2018

Status of Work

Bid evaluation for works contractor has completed, contract signing expected in August 2018.

Objective

This is part of the WMDP that is aimed at improved integrated water resources planning, management and development;and access to and reliability of water and sanitation services.

Description

The scope of works involves;

Ø  Construction of new intake on Namatala stream

Ø  Construction of raw water transmission line to Bunkokho treatment plant

Ø  Rehabilitation of Nabijjo and Nabiyonga intakes

Ø  Rehabilitation and expansion of Bunkokho treatment plant

Ø  Rehabilitation of Manafwa water treatment plant

Ø  Rehabilitation of distribution network in Mbale town

Ø  Bulk transmission of treated water to small towns under MWE (Busolwe, Butaleja; Budaka, Kadama, Kibuku, Tirinyi)

Ø  Construction of distribution system in small towns

Ø  Rehabilitation of sewer lines for the central business district

Contract Amount

USD 34 Million.

Financiers

World Bank

Design & Supervision Consultant

Consulting Engineers Salzgitter

Status of Work

Invitatiom of works contractor has been halted until new World Bank funding is confirmed.

The proposed Integrated Water Management and Development Project (IWMDP) was conceived as a follow on project to the current Water Management and Development Project (WMDP). The proposed project is consistent with the World Bank Group (WBG) Country Partnership Framework (CPF) FY16-17. The proposed project also responds to the Government of Uganda (GoU) vision of a transformed society from a peasant economy to a modern and prosperous country by 2040. The CPF is designed to contribute directly to achieving the Sustainable Development Goals (SDGs) and is guided by the Addis Ababa Action Agenda on financing for development.The project is being developed jointly with the Ministry of Water and Environment with aim of ensuring improvement in water and sanitation services in selected towns. For NWSC, the beneficiary towns are; Mbale, Gulu and Adjumani-Pakele.

Download IWMDP Information sheet     

TERMS OF REFERENCE FOR CONSULTANCY SERVICES FOR FEASIBILITY STUDY, DETAILED DESIGN AND CONSTRUCTION SUPERVISION OF ADJUMANI WATER SUPPLY AND SANITATION PROJECT

DOWNLOAD RESETTLEMENT ACTION PLAN FOR MBALE AND SMALL TOWNS  WATER SUPPLY AND SANITATION PROJECT

TERMS OF REFERENCE FOR CONSULTANCY SERVICES FOR DESIGN REVIEW & CONSTRUCTION SUPERVISION OF MBALE WATER SUPPLY & SANITATION PROJECT

Click here for a detailed Environmental & Social Impact Assessment (ESIA) Report for Mbale

 

Objective

This part of the WMDP that is aimed at improved integrated water resources planning, management and development; and access to and reliability of water and sanitation services

Description

The scope of works involves;

Ø  Rehabilitation and improvement of the Mbale water system including water intake, water treatment plant and water distibution network in Mbale town

Ø  rehabilitation and improvement of sewerage system including sewer network and sewerage treatemnt ponds in Mbale town

Ø  Construction of Karuma-Gulu bulk water transmission mains and water distribution networks for enroute towns of Karuma, Kamdini, Minakulu, Bobi-Palenga and Koro

Ø  Construction of the Adhjumani-Pakele water system including water source, water treatment plant and wayet distribution network

Ø  Construction of sanitation facilities in Adjumani and Pakele towns

Ø Source protection measures for both the existing and new water sources in Mbale, Gulu and Adjumani

Budget

USD 90Million (Mbale 38M, Gulu 28.8M, Adjumani 18M, Source Protection for Arua & Bushenyi 2.6M, and Contigency 2.6M)

Financiers

World Bank

Design & Supervision Consultant

Consulting Engineers Salzgitter

Status of Work 

Project appraisal completed and negotiations over the funding were successfully held between the World Bank and Government of Uganda

Terms of reference  for Mbale Design Review and Supervision consultant were accepted by the world Bank and request for Expression of Interest (REoI) notice published. 

Terms of reference  for Adjumani Design and Supervision consultant were accepted by the world Bank.  

Design for the Gulu component is ongoing (under KfW funded Gulu IPILC Phase 2)

Completion Dates

Mbale

Substantial Completion (June 2022)

Final Completion ( June 2023)

Gulu

Substantial Completion (September 2021)

Final Completion (September 2022)

Adjumani

Substantial Completion (March 2022)

Final Completion (March 2023)

 

Objective

The project aims at improvement of water supply and sanitary services in Albertine Region operational areas of Hoima and Masindi and possible expansion of watsan services in nearby small towns that are not currently serviced by NWSC

Description

The first project phase covers feasibility study and preliminary design. The results of that work will inform decisions on technical infrastructure requirements and resulting financial needs for the NWSC service areas under investigation.

Contract Amount

Euros 918,000 (Feasibility study)

Financiers

National Water & Sewerage Corporation

Consultant

Gauff/Gauff Consultants (U) Ltd

Status of Work

Borehole Drilling completed.

Feasibiity Study and pre-design report approved.

Works are expected to be funded by World Bank under WMDP Phase 2.

Completion Date

Not yet Known